2021
-
ARCO was founded a few years ago. During this period ARCO has worked with great passion for technology and ambition on various innovative and challenging projects to become the professional company they are today. A beautiful and busy period, with satisfying results!
Today we reached a new milestone; we started the construction work for our new business building. Our new headquarter will give us all the space we need to keep on growing, so that we can continue to innovate! Mid 2022 is the date to remember! From then on ARCO operates from the Horsterweg in Grubbenvorst!
-
9 November
Construction has started
The foundation made by Bouwbedrijf John van Gestel BV is already done. On to step 2: placement of the steel structures. -
8 December
Step 2: steel structure
We finished step 2 of the new building. The steel structure is completed. Thanks to the excellent preparations of the steelwork by JSB Horst and the crane skills of Haegens transport, the parts have been placed effortlessly.
2022
-
16 February
We have reached the highest point!
Step 3 of our new building is completed. The floor is poured by Van Berlo; Experts in foundations and floors and the curtain wall around the entire building has been placed by Quick-Steel B.V.
We are currently working on the office area. This part of the building will have a complete glass front. The first windows are already been placed.
-
22 February
Work meeting interior stylist
Creativity forms the basis for a surprising layout of our new working environment. Together with our stylist from Kim & Co, we had the last work meeting for the materials of our new interior. Exciting!
-
31 March
Final touch
The men from Raedts are working hard to finish our new building before the 1th of June 2022, so that we can get started with the interior after that. They are currently working on the curtain wall at the front of the building. They are also working on the finishing touch of the factory hall.
Swipe from left to right to view the photos.
-
9 June
Details make the design
Our beautiful new business location is also starting to take shape. Kim & Co. – interieurarchitectuur has chosen a fitting color palette to give our customers and employees a warm welcome after the moving day.
Swipe from left to right to view the photos.
-
20 June
Packing has begun
For several weeks we have been working hard to prepare everything for the official move. Also last weekend our colleagues worked really hard.
From July 1 we will be located at Horsterweg 84 in Grubbenvorst.
We are looking forward to it!
Swipe from left to right to view the photos.
-
27 June
Visibility property - Check
Our logo has been placed on our new location, and it looks fantastic. We are very proud of the result, what do you think?
Swipe from left to right to view the photos.
-
4 July
It's a wrap!
After a little year, our new building is a fact! Last weekend we officially moved to our new workplace. We are so PROUD!
Raedts, Sijbers Support Elektrotechniek, Van Tilburg Energie Design, Bouwtechnisch ingenieursbureau Christiaens en Wijers, Kim & Co. – interieurarchitectuur and all other companies that helped, thank you very much for your effort and time!
Making Progress Together!